Pre-shipment inspection should produce evidence, not only a statement that the machine is ready. A useful inspection record ties each check to a machine serial number, configuration, test material, measured result, and responsible person.
Mechanical and electrical release
The mechanical release should confirm frame condition, guarding, clamping, guide alignment, lubrication, fastener torque where specified, and safe access. The electrical release should match the approved drawing and destination voltage.
- Machine identity, serial number, model, and approved configuration.
- Guard fixing, emergency stop, door interlocks, and moving-part clearance.
- Motor rotation, sensor position, PLC inputs and outputs, and safety circuit.
- Voltage, frequency, phase, control transformer setting, and terminal labeling.
- Lubrication points, pneumatic pressure, leaks, and protection from chips or coolant.
Performance test and packing evidence
The performance test should use material and operating conditions close to the intended application. Record the measured values and keep photos or video that show the machine configuration, test piece, instrument reading, and final packing.
| Record | Minimum content |
|---|---|
| Test material | Alloy, section or billet size, condition, and quantity |
| Test result | Cycle time, dimensions, tolerance, surface condition, and any adjustment |
| Packing | Protective treatment, fixing points, moisture protection, markings, and package list |
| Release | Open issues, approved deviations, inspection date, and sign-off |
Documents to close the loop
The final document set should identify the exact machine and make installation and maintenance practical. Confirm the language, file format, revision, and whether electrical drawings and manuals are supplied in printed and digital form.
Selection questions
Should inspection happen before or after packing?
Mechanical, electrical, and performance checks happen before packing. Packing and shipping-mark checks happen after packing but before the container is closed.
What if a test value is outside the agreed range?
The record should show the measured value, the cause, the corrective action, the retest result, and whether the buyer approved the final condition.
Are photos enough as inspection evidence?
Photos support the record but do not replace measured values, serial identification, test conditions, and sign-off.